In June - July 2011 the following works are finished:
- Demolition of reinforced concrete, lined with stone, on Lady Strangford Str.
- Removing of facing and paving slabs of limestone on Lady Strangford Str.
- Demolition of the concrete under the stone pavements under the presentation centre.
- Moulding and shaping of new concrete slabs and columns.
- Reinforcement works and concrete works.
- Demolition of concrete under the existing pavement of coloured concrete blocks.