Български
Ancient Philippopolis
Ancient Stadium of Philippopolis
Visit the Ancient Stadium
News and Events
About the Project
Funding and Partners
The Architectural Project
Project Realisation
Construction Works May-June 2011
Construction Works June-July 2011
Construction Works August-September 2011
Construction Works October-November 2011
Construction Works - January-February 2012
Construction Works - March 2012
Construction Works - April 2012
Ad Hoc Center for Urban Archaeology
Information and Bibliography
Logo & Identity
Website
Home
/
About the Project
/
Project Realisation
/ Construction Works - April 2012
Construction Works - April 2012
In April 2012 the following works are done:
Installation of equipment and lighting.
Installation of public stairs.
Installation of elevator.
Glass walls of the presentation centre.
Tweet
Сфендоната - поглед отгоре / Д. Костадинова
Поглед към презентационния център и пилоните на акведукта / Д. Костадинова
Подземната улица - поглед към пистата / Д. Костадинова
Крепостната стена и стълбата към презентационния център / Д. Костадинова
Входа на презентационния център и асансьора / Д. Костадинова
Обсъждане на довършителните работи / Д. Костадинова
Зидани канали / К. Върбанов